Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document
control process to manage all documentation requirements. The document control process was
created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an
organization-wide configuration management role. The MFH Quality Manager will administer the
configuration management procedure for the Restructuring project since this must comply with the
MFH document control process.
What additional risk will this place on the project?

PrepAway - Latest Free Exam Questions & Answers

A.
None because risks associated with the centralization and rationalization of the Facilities Division will be
managed by another project.

B.
These changes will delay stage 3 by three weeks.

C.
There is only £70k left in the project change budget.

D.
The reduced value of the contracted services required by the Outsourcing project may result in an
insufficient number of proposals being received.