Exam PR2P: PRINCE2 Practitioner

Which statement applies to the Information needs for ea…

Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in
the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have
been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively
simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project
process. No Project Brief has been produced. Instead the Project Manager used the project mandate to
produce a simple Project Initiation Documentation (PID). The PID includes the Business Case, a product
checklist and several Product Descriptions, Including the Project Product Description. Short sections are also
included for each of the strategies and the controls to be applied. The Project Manager has elected to use the
Daily Log to record all risks, issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be
authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will
support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the
Communication Management Strategy provided in the additional information.
Which statement applies to the Information needs for each interested party section?A. Delete entry 13 because the activity to provide the weekly updates should be scheduled in the relevant
Stage Plan.

Which statement applies to the Stakeholder analysis: In…

Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in
the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have
been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively
simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project
process. No Project Brief has been produced. Instead the Project Manager used the project mandate to
produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product
checklist and several Product Descriptions, Including the Project Product Description. Short sections are also
included for each of the strategies and the controls to be applied. The Project Manager has elected to use the
Daily Log to record all risks, issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be
authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will
support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the
Communication Management Strategy provided in the additional information.
Which statement applies to the Stakeholder analysis: Interested parties section?

Which statement applies to the Timing of communication …

Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in
the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have
been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively
simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project
process. No Project Brief has been produced. Instead the Project Manager used the project mandate to
produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product
checklist and several Product Descriptions, Including the Project Product Description. Short sections are also
included for each of the strategies and the controls to be applied. The Project Manager has elected to use the
Daily Log to record all risks, issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be
authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will
support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the
Communication Management Strategy provided in the additional information.
Which statement applies to the Timing of communication activities section?

What statement applies to the Records section?

Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in
the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have
been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively
simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project
process. No Project Brief has been produced. Instead the Project Manager used the project mandate to
produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product
checklist and several Product Descriptions, Including the Project Product Description. Short sections are also
included for each of the strategies and the controls to be applied. The Project Manager has elected to use the
Daily Log to record all risks, issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be
authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will
support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the
Communication Management Strategy provided in the additional information.
What statement applies to the Records section?