The risk management team of a software project has decided that due to the lack of adequate
talent in the company, development of a specific part of the system is under high risk, so the team
has decided to outsource it. This is an example of which risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Transfer

B.
Share

C.
Avoid

D.
Accept