Which input to Collect Requirements is used to identify stakeholders who can provide information on requiremen

Which input to Collect Requirements is used to identify stakeholders who can provide information
on requirements?

PrepAway - Latest Free Exam Questions & Answers

A.
Stakeholder register

B.
Scope management plan

C.
Stakeholder management plan

D.
Project charter