To which process is work performance information an input?
A. Administer Procurements
B. Direct and Manage Project Execution
C. Create WBS
D. Perform Qualitative Risk Analysis
2 Comments on “which process is work performance information an input?”
felixsays:
answer should be B
0
0
Ivasays:
According Test King, “B” is the correct answer, but work performance information is an output in Direct and Manage project work.
About Answer: A – Inputs of Administer Procurement Process are:
contract, other procurement documents and work performance information
answer should be B
0
0
According Test King, “B” is the correct answer, but work performance information is an output in Direct and Manage project work.
About Answer: A – Inputs of Administer Procurement Process are:
contract, other procurement documents and work performance information
0
0