2 Comments on “which process is work performance information an input?

  1. Iva says:

    According Test King, “B” is the correct answer, but work performance information is an output in Direct and Manage project work.
    About Answer: A – Inputs of Administer Procurement Process are:
    contract, other procurement documents and work performance information