Which of the following are inputs to the Plan Procurements process?
A.
Risk register, scope baseline, enterprise environmental factors, organizational process assets,
project schedule
B.
Risk register, scope baseline, make-or-buy decisions, organizational process assets, project
schedule
C.
Project management plan, qualified seller list, contract, enterprise environmental factors,
teaming agreements
D.
Project management plan, qualified seller list, contract, make-or-buy decisions, teaming
agreements
Which of the following is an input to the Plan Schedule Management process?
a. Pareto diagrams and resource calendars
b. Organizational process assets and the project charter
c. Activity attributes and time tables
d. Gantt charts for the project being planned
The answer is: b