PrepAway - Latest Free Exam Questions & Answers

Which of the following events would result in a baseline update?

Which of the following events would result in a baseline update?

PrepAway - Latest Free Exam Questions & Answers

A.
A project is behind schedule and the project manager wants the baseline to reflect estimated
actual completion.

B.
A customer has approved a change request broadening the project scope and increasing the
budget.

C.
One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.
One of the key project team resources has left the team and no replacement is available.


Leave a Reply