Inputs to the Plan Risk Management process include the:
A. cost management plan.
B. risk management plan,
C. activity list,
D. risk register.
2 Comments on “Inputs to the Plan Risk Management process include the:”
mattsays:
none of the above, PMBOK pg 313
0
0
geraldyonsays:
One of the input to the Plan Risk Management is a Project Management Plan. And the “Cost Management Plan” is a subsidiary plan of the Project Management Plan; so as the Risk Management Plan, but the process in question is the Plan Risk Management, which obviously means that the only possible answer is the “Cost Management Plan”.
none of the above, PMBOK pg 313
0
0
One of the input to the Plan Risk Management is a Project Management Plan. And the “Cost Management Plan” is a subsidiary plan of the Project Management Plan; so as the Risk Management Plan, but the process in question is the Plan Risk Management, which obviously means that the only possible answer is the “Cost Management Plan”.