When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups wo

When large or complex projects are separated into distinct phases or subprojects, all of the
Process Groups would normally be:

PrepAway - Latest Free Exam Questions & Answers

A.
divided among each of the phases or subprojects.

B.
repeated for each of the phases or subprojects.

C.
linked to specific phases or subprojects.

D.
integrated for specific phases or subprojects.