Change requests, project management plan updates, project document updates, and
organizational process assets updates are all outputs of which project management process?

A.
Plan Risk Responses
B.
Manage Stakeholder Expectations
C.
Define Scope
D.
Report Performance
Following are the outputs of manage stakeholder Engagement.
.1 Issue log
.2 Change requests
.3 Project management plan updates
.4 Project documents updates
.5 Organizational process assets updates.