Which of the following tools best provides transparency into the progress throughout the sprint?

A development team has finished identifying the tasks they will be accountable for during
the next sprint. Which of the following tools best provides transparency into the progress
throughout the sprint?

PrepAway - Latest Free Exam Questions & Answers

A.
Burndown chart

B.
Gantt chart

C.
Hours expended chart

D.
Management baseline chart