how are planning outputs shared with stakeholders?

In Agile projects, how are planning outputs shared with stakeholders?

PrepAway - Latest Free Exam Questions & Answers

A.
Using the most highly visible method possible

B.
On a need-to-know basis depending on role

C.
According to the project communications plan

D.
Through a series of stakeholder meetings