PrepAway - Latest Free Exam Questions & Answers

Is this an appropriate approach to running Daily Scrums?

A ScrumMaster consistently holds Daily Scrums and keeps them to 15 minutes or less. The
ScrumMaster brings a list of assigned tasks and checks the status of each task with the
relevant team members. The ScrumMaster then assigns new tasks for the day and ends the
meeting. Is this an appropriate approach to running Daily Scrums?

PrepAway - Latest Free Exam Questions & Answers

A.
Yes, the ScrumMaster should get status updates and distribute new tasks to the team.

B.
Yes, the ScrumMaster should hold Scrums daily and keep the time to 15 minutes or less.

C.
No, the ScrumMaster should act in the role of facilitator to foster team self-organization.

D.
No, the ScrumMaster should allow the Scrum to run as long as is required by the team.