Agile project development processes typically:

Agile project development processes typically:

PrepAway - Latest Free Exam Questions & Answers

A.
Encapsulate analysis, design, code, and test within an iteration.

B.
Document each business process individually and in detail.

C.
Use a Gantt chart with well-defined activities, responsibilities, and time frames.

D.
Map the iteration backlog to a Work Breakdown Structure (WBS).