Issue change requests and adapt approved changes into the project’s scope, plans, and
environment is an activity included in which of the following project management processes?

A.
Direct and Manage Project Execution
B.
Monitor and Control Project Work
C.
Perform Integrated Change Control
D.
Monitor and Control Risks