Which of the following is a tool and technique for activity duration estimating?

A.
Parametric estimating
Functional
B.
Monte Carlo analysis
Projectized
C.
Top-down estimating
Weak Matrix
D.
Bottom-up estimating
Balanced Matrix
A.
Parametric estimating
Functional
B.
Monte Carlo analysis
Projectized
C.
Top-down estimating
Weak Matrix
D.
Bottom-up estimating
Balanced Matrix
Explanation:
QUESTIONNO: 734
A project manager’s authority is limited within which of the following organizational structures?
Correct answer is A. Parametric Estimating – Pg. 166 of PMBoK 5th Ed.