Which of the following are three inputs to the risk register?
A.
Risk register updates, stakeholder register, and quality management plan
B.
Communication management plan, enterprise environmental factors, and activity duration
estimates
C.
Risk management plan, activity cost estimates, and project documents
D.
Project scope statement, organizational process assets, and scope baseline

I don’t get it. There are not inputs to “risk register”. Risk register by itself is an input to Plan Risk Responses. Somebody to explain, please.
0
0
Risk register is output of “identify risks” processes.
therefore, here are inputs of identify risks processes.
.1 Risk management plan
.2 Cost management plan
.3 Schedule management plan
.4 Quality management plan
.5 Human resource
management plan
.6 Scope baseline
.7 Activity cost estimates
.8 Activity duration estimates
.9 Stakeholder register
.10 Project documents
.11 Procurement documents
.12 Enterprise environmental
factors
.13 Organizational process assets