When estimating initial velocity, the team should most likely:

A.
Discuss among the team their expectations of how many story points they can address.
B.
Discuss with the customer their expectation for the velocity of producing the product.
C.
Use a Kanban workflow to identify steps and calculate velocity.
D.
Use velocity of past iterations or make a calculated guess.