A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule
activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated
to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

PrepAway - Latest Free Exam Questions & Answers

A.
Three weeks

B.
Four weeks

C.
Five weeks

D.
Six weeks