What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual
cost (AC) is $50, and the earned value (EV) is $25?
A.
$50
B.
$100
C.
$125
D.
$175
You must be logged in to post a comment.
EAC = AC + (BAC – EV)