The process of monitoring the status of the project to update project progress and manage
changes to the schedule baseline is:

A.
Control Schedule.
B.
Quality Control.
C.
Perform Integrated Change Control.
D.
Develop Schedule.
You must be logged in to post a comment.
Control Schedule—The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
Page 141 PMBook.