Who, along with the project manager, is suppo…

Who, along with the project manager, is suppo

sed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

A.The customer and functional managers

B.The risk owners and stakeholders

C.The sponsors and stak

eholders

D.The project management team