The process of monitoring the
status of the project to update project progress and manage changes to the schedule baseline is:
A.Control Schedule.
B.Quality Control.
C.Perform Integrated Change Control.
D.Develop Schedule.
The process of monitoring the
status of the project to update project progress and manage changes to the schedule baseline is:
A.Control Schedule.
B.Quality Control.
C.Perform Integrated Change Control.
D.Develop Schedule.