PrepAway - Latest Free Exam Questions & Answers

The project manager at an organization has just realized that some of the engineering staff has been allocated

The project manager at an

organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project

on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the managers disposal?

A.Resource leveling and fast tracking

B.Fast tracking and crashing

C.Crashing and applying leads and lags

D.Scheduling tools and ap

plying leads and lags


Leave a Reply