The project manager at an
organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project
on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the managers disposal?
A.Resource leveling and fast tracking
B.Fast tracking and crashing
C.Crashing and applying leads and lags
D.Scheduling tools and ap
plying leads and lags