Project contracts generally fall into which of the following three broad categories?
A.Fixed-price, cost reimbursable, time and materials
B.Make-or-buy, margin analysis, fixed-price
C.Time and materials,
fixed-price, margin analysis
D.Make-or-buy, lump-sum, cost-plus-incentive