The project has a current cost performance index of 0.80. Assuming thi…

The project has a current cost performance index of 0.80. Assuming thi

s performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

A.$800

B.$1000

C.$1250

D.$1800