Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
A.WBS directory
B.Activity list
C.WBS
D.Project schedule
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
A.WBS directory
B.Activity list
C.WBS
D.Project schedule