Perform Integrated Change Control is the process of:
A.Reviewing, approving, and managing all change requests
B.Facilitating change management, manuals, or automation tools
C.Comparing actual results with planned results in order to
expand or change a project
D.Documenting changes according to the change control system by the change control board