The project budget is set at $150,000. The project duration is planned to be one year. At the completi…

The project budget is set at $150,000. The project duration is planned to be one year. At the completi

on of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

A.0.8

B.0.89

C.1.13

D.1.25