PrepAway - Latest Free Exam Questions & Answers

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the pr

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

A.Utilize the change control process.

B.Crash the

schedule to fix the defect.

C.Leave the defect in and work around it.

D.Fast-track the remaining development.