PrepAway - Latest Free Exam Questions & Answers

Which technique is utilized in the Control Schedule process?

Which technique is

utilized in the Control Schedule process?

A.Performance measure

B.Baseline schedule

C.Schedule network analysis

D.Variance analysis


Leave a Reply