Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform
Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
A.Initiating
B.Monitoring and Controlling
C.Planning
D.Closing