Which of the following involves making information available to project stakeholders in a timely manner?
A.Plan Communications
B.Performance reporting
C.Project status reports
D.Distribute Information
Which of the following involves making information available to project stakeholders in a timely manner?
A.Plan Communications
B.Performance reporting
C.Project status reports
D.Distribute Information