Which of the following events would result in a baseline update?

Which of the following events would result in a baseline update?

A.A project is behind schedule and the project manager wants the baseline to reflect

estimated actual completion.

B.A customer has approved a change request broadening the project scope and increasing the budget.

C.One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.One of the key project team r

esources has left the team and no replacement is available.