Which of the following correctly explains the term -progressive elaboration?
A.Changing project specifications continuously
B.Elaborate tracking of the project progress
C.Elaborate tracking of the project spe
cifications with a change control system
D.Project specifications becoming more explicit and detailed as the project progresses