When is a project finished?
A.After verbal acceptance of the customer or sponsor
B.After lessons learned have been documented in contract closure
C.When the project objectives have been met
D.Afte
r resources have been released
When is a project finished?
A.After verbal acceptance of the customer or sponsor
B.After lessons learned have been documented in contract closure
C.When the project objectives have been met
D.Afte
r resources have been released