What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,00

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

A.1

B.0.4

C.0.5

D.0.8