What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $5

What is the

estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A. $50

B. $100

C. $125

D. $175