What are the identified risks for doing excessive decomposition in a WBS?

What are the identified risks for doing excessive decomposition in a WBS?

A.Insufficient project funding and disqualification of sellers

B.Insufficient project funding a

nd ineffective use of resources

C.Disqualification of sellers and non-productive management efforts

D.Non-productive management effort and inefficient use of resources