The Verify Scope process is primarily concerned with:

The Verify Scope process is primarily concerned with:

A.formalizing acceptance of the completed project deliverables.

B.accuracy of the work deliverables.

C.form

alizing approval of the scope statement.

D.accuracy of the work breakdown structure (WBS).