The technique of subdividing project deliverables into smaller, more manageable components until the work and
deliverables are defined to the work package level is called:
A.a control chart.
B.baseline.
C.Create WBS.
D.decomposition.
The technique of subdividing project deliverables into smaller, more manageable components until the work and
deliverables are defined to the work package level is called:
A.a control chart.
B.baseline.
C.Create WBS.
D.decomposition.