The methodology that combines scope, schedule, and
resource measurements to assess project performance and progress is known as:
A.Earned value management.
B.Forecasting.
C.Critical chain methodology.
D.Critical path methodology.
The methodology that combines scope, schedule, and
resource measurements to assess project performance and progress is known as:
A.Earned value management.
B.Forecasting.
C.Critical chain methodology.
D.Critical path methodology.