The
definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
A. Timing
B. Methodology
C. Risk categories
D. Budgeting
The
definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
A. Timing
B. Methodology
C. Risk categories
D. Budgeting