The component of the risk management plan that documents how risk activities will be reco
rded is called:
A.tracking
B.scoping
C.timing
D.defining
The component of the risk management plan that documents how risk activities will be reco
rded is called:
A.tracking
B.scoping
C.timing
D.defining