A projects purpose or justification, measurable project objectives and related success criteria, a summary mil

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all compo

nents of which document?

A.Work breakdown structure

B.Requirements document

C.Project charter

D.Project management plan