A project manager is appointed full-time to a project and is given full-time administrative staff and full-tim

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational

structure?

A. Projectized

B. Weak matrix

C. Functional

D. Balanced matrix