Organizations perceive risks as:
A.events that will inevitably impact project and organizational objectives.
B.the effect of uncertainty
on their project and organizational objectives.
C.events which could have a negative impact on project and organizational objectives.
D.the negative impact of undesired events on their project and organizational objectives.