A measure of cost performance that is required to be achieved with the remaining resources in order to meet a

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for

finishing the outstanding work to the remaining budget is known as the:

A.budget at completion (BAC)

B.earned value management (EVM)

C.to-complete performance index

D.cost performance index