In a construction project schedule, what is the logical…

In a construction project schedule, what is the logical

relationship between the delivery of the concrete materials and the pouring of concrete?

A.Start-to-start (SS)

B.Start-to-finish (SF)

C.Rnish-to-finish (FF)

D.Finish-to-start (FS)