In complex projects/ initiating processes should be completed:
A.Within a work package.
B.In each phase of the project.
C.To estimate schedule constraints.
D.To estima
te resource allocations.
In complex projects/ initiating processes should be completed:
A.Within a work package.
B.In each phase of the project.
C.To estimate schedule constraints.
D.To estima
te resource allocations.